A bar graph with time on the horizontal axis and the resource to be scheduled on the vertical axis is a ________.
A) managerial grid
B) PERT network
C) materials production source graph
D) Gantt chart
E) SWOT analysis
Correct Answer:
Verified
Q90: Which of the following is the fourth
Q91: Briefly discuss the quantitative methods of sales
Q92: Explain the qualitative methods of sales forecasting.
Q93: The major weakness of the Gantt chart
Q94: What is a plan? Describe the four
Q95: Define the program evaluation and review technique
Q96: Explain the critical path of the program
Q98: What is a standing plan and a
Q99: Explain the Delphi method and outline the
Q100: What is a Gantt chart, explain its