Which of the following is false regarding the issue of time under a contract?
A) typically, time is of the essence for both parties
B) since the contractor will be liable for late completion, only he need be concerned with the feasibility of the construction schedule
C) when scheduling, minor tasks should be given as much consideration as major tasks
D) all of the above
Correct Answer:
Verified
Q1: Owners can increase price certainty in fixed-cost
Q2: Why is the name of fixed-price contracts
Q3: The public-private partnership model is most similar
Q5: Which is the typical sequence in which
Q6: A contractor who builds a house and
Q7: What is the key difference between obligations
Q8: Between which of the following parties is
Q9: To establish causation, the plaintiff must show
Q10: Which of the following is a strict
Q11: "A" mistakenly builds his farm boundary fence
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents