What Is the Predicted Indirect Manufacturing Labour Cost If 160

Question 5

Multiple Choice

What is the predicted indirect manufacturing labour cost if 160 machine-hours are budgeted and 170 are actually worked, assuming the estimated cost function is y = $81.04 + 5.32x?


A) $985.44
B) $932.24
C) $904.40
D) $851.20
E) $81.04