Which of the following is NOT a key step in managing bottleneck resources?
A) Recognize that the bottleneck resource determines throughput contribution of the plant as a whole.
B) Search and find the bottleneck resource by identifying resources with large quantities of inventory waiting to be worked on.
C) Keep the bottleneck operation busy and subordinate all nonbottleneck resources to the bottleneck resource.
D) Reduce the number of employees who work in the bottleneck area.
E) Take action to increase bottleneck efficiency and capacity.
Correct Answer:
Verified
Q35: A client in another province needs immediate
Q36: A client in another province needs immediate
Q37: The firm has a $2,000 maintenance contract
Q38: A client in another province needs immediate
Q39: A client in another province needs immediate
Q41: Which of the following sets of sentences
Q42: The Glass Shop, a manufacturer of large
Q43: Palmateer Industries makes an electronic component in
Q44: Brix, Inc., prepares frozen food for fast-food
Q45: Aunt Lydia's Cookies, Inc., prepares frozen gourmet
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents