Solved

For the Buehler Bakery, the Desired Output for a 8

Question 77

Multiple Choice

For the Buehler Bakery, the desired output for a 8 hour workday is 450 units. The discrete tasks required to produce the product have been identified, timed in seconds, and ordered as indicated in the table.
For the Buehler Bakery, the desired output for a 8 hour workday is 450 units. The discrete tasks required to produce the product have been identified, timed in seconds, and ordered as indicated in the table.    -Considering there are 7 work centers for the assembly line and assuming 1 worker per work center, calculate the idle time per day. A) 5.38 hours per day B) 10.37 hours per day C) 16 hours per day D) 32 hours per day E) Need more information to answer the question
-Considering there are 7 work centers for the assembly line and assuming 1 worker per work center, calculate the idle time per day.


A) 5.38 hours per day
B) 10.37 hours per day
C) 16 hours per day
D) 32 hours per day
E) Need more information to answer the question

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents