Production reports range from source documents to key metrics. Which is the best description of a master production schedule (MPS) ?
A) A long-term plan depicting what will be produced and when based on customer product demand and allocation of resources
B) A list of raw materials, steps, and parts needed to manufacture a product
C) A list of sequential steps followed to manufacture a product
D) A build plan that compiles planned orders into a short-term schedule
Correct Answer:
Verified
Q75: What is one of the key tables
Q76: What is one of the key tables
Q77: Production reports range from source documents to
Q78: Production reports range from source documents to
Q79: Production reports range from source documents to
Q81: Production reports range from source documents to
Q82: Production reports range from source documents to
Q83: Production reports range from source documents to
Q84: Production reports range from source documents to
Q85: Production reports range from source documents to
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents