What are the two types of progress controls provided by PRINCE2?
1) Stage-driven
2) Tolerance-driven
3) Time-driven
4) Event-driven
A) 1, 2
B) 1, 4
C) 2, 3
D) 3, 4
Correct Answer:
Verified