Which of the following products are part of the Project Initiation documentation?
1) Quality Management Strategy
2) Project Plan
3) Outline Business Case
4) Communication Management Strategy
A) 1, 2
B) 2, 3
C) 1, 3, 4
D) 1, 2, 4
Correct Answer:
Verified
Q8: Which role maintains the Quality Register?
A)Project Support
B)Project
Q9: Who is responsible for determining the Change
Q10: Which document is used to record issues
Q11: Which process allows non-PRINCE2 practices to be
Q12: Which of the following are tolerance areas?
1)Change
2)Issues
3)Quality
4)Benefits
A)1,2
B)2,3
C)2,4
D)3,4
Q14: Which of the following statements is true
Q15: Who can order the closure of a
Q16: Which role(s) has/have ultimate authority on the
Q17: Which roles must be independent of each
Q18: Which process provides information to the Project
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents