Josh Is Working on a Brand New Program, Need a Date!

Question 65

Multiple Choice

Josh is working on a brand new program, Need a Date!, and he's going to be performing the following processes for the first time for his program. Which is the first process he should perform?


A) Create PWBS
B) Schedule Development
C) Scope Definition
D) Transition Planning

Correct Answer: