Five days after starting a work task, the supervisor assesses that the task is 25% completed. If no other information is available, what is the estimated time remaining for the task:
A) 10 days
B) 15 days
C) 20 days
D) cannot be estimated
Correct Answer:
Verified
Q1: The EV represents, at a given time:
A)
Q2: Suppose a project was originally estimated to
Q3: Which of the following might project managers
Q4: Activity X has four immediate predecessors, three
Q5: To implement a time buffer (circle one):
A)
Q7: Among important ways to assess the status
Q8: Which of the following are true about
Q9: In controlling projects, data on actual project
Q10: Often, the impact of changing system requirements
Q11: Ways to control the adverse impact of