The forward and backward pass:
A) determine the early and late start dates of activities, respectively.
B) determine the float (slack) of activities.
C) determine the critical path.
D) all of the above.
E) (a) and (c) above
Correct Answer:
Verified
Q11: If Activity A has to be performed
Q12: The critical path:
A) is shortest path through
Q13: In a start-to-start relationship, a 2-day lag
Q14: The criticism of network techniques that some
Q15: Resource leveling:
A) makes use of float (slack)
Q17: In the PDM method (circle all that
Q18: Statement: The term "dummy activity" is a
Q19: Statement: Redundant activities are activities that are
Q20: Statement: There can only be one critical
Q21: Statement: If an activity has multiple predecessors,