The operations manager of the university cafeteria has noticed that about 65 percent of the mistakes made occur during the last 2 hours of employees' shifts, 20 percent occur during the midday time slot, 10 percent occur during the morning time slot, and 5 percent of the errors occur during the other time periods of the day. Which SPC tool would the manager most likely obtain this information from?


A) a Pareto chart
B) an Ishikawa diagram
C) a run chart
D) a flowchart