When submitting an RFI, the Contractor should if possible
A) provide proof that the design is deficient
B) submit pricing
C) submit a preferred solution
D) ask for an immediate meeting to resolve the issue so the schedule will not be affected
Correct Answer:
Verified
Q8: Contracts are usually written
A) to get more
Q9: Could be part of the contract
A) General
Q10: There are two types of ambiguities-patent and
A)
Q11: Two clauses that help interpret the contract
Q12: The first level of interpreting a Contract
Q14: Although many may have a say, a
Q15: Cardinal changes
A) can be based on scope
Q16: Liquidated damages result from
A) water damage usually
Q17: Means and methods will
A) always be provided
Q18: The Spearin Doctrine
A) relieves the Contractor from
Unlock this Answer For Free Now!