Which of the Following Statements Is True of Critical Path

Question 56

Multiple Choice

Which of the following statements is true of Critical Path Method (CPM) ?


A) Activities on the critical path take the shortest time to be completed.
B) It determines the critical path for the completion of a series of interrelated activities.
C) Activities that are on the critical path are flexible and can be delayed without delaying a project.
D) A delay in the activities of a project does not affect the scheduled delivery of the project.