​In a PERT/CPM Chart When Several Tasks Are in Sequence

Question 38

Multiple Choice

​In a PERT/CPM chart when several tasks are in sequence to form a path segment but are not on the critical path the total slack time is _____?


A) the same for each one
B) ​the sum of the individual slack times
C) ​equal to the greatest slack time  
D) ​equal to the smallest slack time