Tasks A, B, and C have a duration of two days. Task D has a duration of three days, and Task E has duration of four days. Task A starts on Day 1, and Task B starts on Day 2. Task C starts after Task A. Tasks D and E start after Task C. Which of the following is the critical path if Task B starts on Day 3?
A) A, C, D
B) A, C, E
C) A, D, E
D) B, C, E
Correct Answer:
Verified
Q515: An approved change was implemented. Which of
Q516: A company recently went through a project
Q517: An active project is focused on quality
Q518: During planning, a project coordinator publishes the
Q519: Company A and Company B have come
Q521: A project manager is determining a project's
Q522: A company recently discovered that it could
Q523: A project team is spread between two
Q524: A project team is not delivering their
Q525: While working on risk ranking, the project
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents