Tasks A and B have a duration of two days. Task A starts on Day 1, and Task B starts on Day 3. Tasks C and D have a duration of three days, and Task E has a duration of four days. Task C starts after Task A. Task D and E start after Task C. If Task A starts on December 15, which of the following is the anticipated start date for Task D?
A) December 18
B) December 19
C) December 20
D) December 21
E) December 22
Correct Answer:
Verified
Q509: A project manager has set aside a
Q510: A project manager wishes to track a
Q511: The supervisor asks an engineer to be
Q512: A small company has a successful proof
Q513: A stakeholder informs a project manager that
Q515: An approved change was implemented. Which of
Q516: A company recently went through a project
Q517: An active project is focused on quality
Q518: During planning, a project coordinator publishes the
Q519: Company A and Company B have come
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents