During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor's tasks. The project team has just informed the project manager their activities are almost complete, and they would like permission to begin testing. The vendor is not scheduled to deliver the products for two months. Which of the following should have occurred to prevent this issue?
A) During the planning phase, the project manager should have recognized the relationship between the vendor's and project team's tasks and adjusted the schedule for the project team to begin activities two months later.
B) The project manager should have crashed the schedule for the vendor to keep it at the same work pace as the rest of the project team.
C) During the project team's regular status meeting with the vendor, the project team should have informed the vendor that the team was ahead of schedule and to speed up their work.
D) During the project team's regular status meeting with the vendor, the vendor should have informed the project team that it required another two months, and to slow down.
Correct Answer:
Verified
Q467: A PM notes a feature that was
Q468: There is a project in which the
Q469: In which of the following organizational structures
Q470: A project manager needs to identify the
Q471: Which of the following should be included
Q473: A project's stakeholders have not been informed
Q474: A project manager is collecting the number
Q475: During a CCB, a SME evaluated the
Q476: Which of the following represents the order
Q477: A project sponsor approaches the project manager
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents