Project a Is Delivering the Foundation for Project B

Question 390

Multiple Choice

Project A is delivering the foundation for Project B. Construction regulations have changed during Project A, requiring work to be redone in the allocated buffer. Which of the following is the MOST likely impact to Project B?


A) The cost will increase.
B) There will be no impact.
C) The scope will change.
D) The schedule will change.