The project manager is running a project in an organization with a strong PMO and a mature control process. Due to vendor delays, the project is scheduled to exceed the authorized timeline. The project manager has discovered that fast-tracking two tasks will mitigate the issue. Which of the following should the project manager do NEXT?
A) Announce the fast track to the project team.
B) Modify the schedule
C) Initiate a change request.
D) Obtain approval.
Correct Answer:
Verified
Q362: A highly skilled project engineer will be
Q363: A vendor is late with product deliverables.
Q364: Which of the following are characteristics of
Q365: A project sponsor promises the Chief Executive
Q366: A project is running behind schedule. To
Q368: A member of a CCB notices a
Q369: Which of the following are characteristics of
Q370: Which of the following events would MOST
Q371: The government wants to start a project
Q372: A company has completed its annual strategic
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents