The PM has requested that a project repository be developed. Sensitive information will be available on the site that could affect the project's success. Only personnel who need to know the information will have access. Which of the following site types is the PM requesting?
A) Wiki page
B) Intranet
C) Extranet
D) Internet
E) Knowledge base
Correct Answer:
Verified
Q300: Which of the following documents will provide
Q301: Which of the following tasks are responsibilities
Q302: Which of the following are the roles
Q303: Ann, a project manager, is working for
Q304: A project manager is assigned a project
Q306: Risk ID 2 has occurred.
Q307: Which of the following provides tools and
Q308: A fire alarm goes off in the
Q309: Which of the following should a project
Q310: A project sponsor has requested documentation to
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents