Question 299

Multiple Choice

Task A starts on Day 1 and has a duration of two days. Task B has a duration of two days and starts on Day 3. Task C starts after Task A and has a duration of three days. Task D starts after Task B and Task C and has a duration of one day. Which of the following represents the critical path?


A) Five days
B) Six days
C) Seven days
D) Eight days