Question 229

Multiple Choice

A project manager is creating the monthly report for top management. The project manager has collected the information below: AC = 100 PV = 80 EV = 120 Based on this information, the CPI reflects which of the following about the project?


A) It is under budget.
B) It is over budget.
C) It is ahead of schedule.
D) It is behind schedule.