An organization needs a vendor to provide a solution. The organization can only describe its goals but not how to accomplish the work. Which of the following types of procurement should be used?
A) Request for information
B) Request for quote
C) Request for bid
D) Request for proposal
Correct Answer:
Verified
Q162: Due to a lack of adherence to
Q163: A project sponsor, project manager, and project
Q164: The Chief Executive Officer (CEO) has announced
Q165: The project manager needs to motivate the
Q166: A project manager needs status on the
Q168: Under an Agile methodology, standup meetings occur:
A)
Q169: Upper management asks a project sponsor to
Q170: A project sponsor wants to know when
Q171: Which of the following describes some of
Q172: Which of the following project phases would
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents