Solved

A Project Manager Is Trying to Ensure the Quality of the Design

Question 111

Multiple Choice

A project manager is trying to ensure the quality of the design and reduce the number of potential defects. The project manager would like to use the fishbone diagram to perform this analysis. This type of modeling relies on:


A) Prioritizing the specific event.
B) Variance in the process over time.
C) Causes of a specific event.
D) Determining the number of events.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents