A Non-Stakeholder Approaches the Project Manager and Asks If Certain

Question 96

Multiple Choice

A non-stakeholder approaches the project manager and asks if certain items can be added to a project that was started two months earlier. Which of the following constraints does this impact MOST?


A) Time
B) Schedule
C) Scope
D) Cost

Correct Answer: