During a project assessment, a project manager determines the initial project cost estimates were incorrect, and there is not enough budget left, including reserves, to complete the project. Which of the following actions should the project manager take?
A) Alert the project sponsor of the situation.
B) Contact the customer and request more funding.
C) Announce the project will end early due to lack of funds.
D) Attempt to save money in downstream activities.
Correct Answer:
Verified
Q18: The executive sponsor asks a project manager
Q19: After identifying all known tasks, the project
Q20: The PMO is responsible for: (Choose two.)
A)
Q21: During the execution phase of a project,
Q22: Which of the following is a definition
Q24: A customer will have ongoing changes to
Q25: Two team members have concluded that documentation
Q26: A project team is overseeing the installation
Q27: Which of the following project documents should
Q28: Several team members report that meeting objectives
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents