Sam is preparing for the task of prioritizing requirements and he'll need five inputs to accomplish the task. Which one of the following is not an input that Sam will use to prioritize requirements?
A) Risk analysis
B) Business need
C) Requirements management plan
D) Business case
Correct Answer: