The ____ is the cost of the element divided by its quantity.
A) piece rate
B) single-rate
C) variable rate
D) unit rate
Correct Answer:
Verified
Q10: An elemental cost analysis of a finished
Q11: In order to obtain a realistic assessment
Q12: When a developer first considers the idea
Q13: When using an elemental analysis as an
Q14: The _ contingency is an amount that
Q15: Very little information is required about a
Q16: A trade breakdown is not detailed enough
Q17: An element represents a component that always
Q19: The _ UniFormat is a function-based elemental
Q20: All that is required to prepare a