Is a Structured Approach for Organising All the Project Work

Question 91

Multiple Choice

is a structured approach for organising all the project work and deliverables into logical groupings and subdividing them into more manageable components to help ensure that all the work and deliverables to complete the project are identified and included in the baseline project plan.


A) Assigning responsibilities in a responsibility assignment matrix
B) Obtaining agreement for the project scope document
C) Creating a work breakdown structure
D) Finalising the project quality plan

Correct Answer:

verifed

Verified