Which of the following is not a limitation of PERT and similar project-scheduling techniques?
A) They force the manager to organize and quantify information.
B) One or more important activities may be omitted from the network.
C) Precedence relationships may not all be correct as shown.
D) Time estimates may contain a "fudge factor."
E) The use of a computer is essential for large projects.
Correct Answer:
Verified
Q56: Suppose a project is subject to the
Q57: Which of the following would probably not
Q58: Which of the following is not a
Q59: In a project network, the critical path
Q60: A popular visual tool for planning and
Q62: The project management strategy of injecting additional
Q63: Activity 4-5 in a network diagram has
Q64: When developing probabilistic estimates of project duration,
Q65: The basis for use of the beta
Q66: Which of the following are limitations of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents