Andrew, a Carpenter, Entered into a Contract with Steven for the Construction

Question 27

True/False

Andrew, a carpenter, entered into a contract with Steven for the construction of a garage on Steven's property for $5,000. Andrew had constructed the entire garage except for a small door, when he refused to complete the contract. Andrew would not be entitled to claim payment, because he has not finished his part of the agreement.