You have just been given a project that has a specific completion date. After a discussion with top management you find that while the date is important the cost is more important and a slip in delivery would be acceptable if required to meet the cost targets. The completion date is best classified as
A) constrained.
B) reduced.
C) accepted.
D) limited.
E) optional.
Correct Answer:
Verified
Q28: The final step in defining a project
Q29: A project professional has just been assigned
Q30: After reviewing the project scope statement, the
Q31: Five steps are involved when defining a
Q32: There are 5 steps involved when defining
Q34: A project professional is viewing a document
Q35: Within any project, the first step of
Q36: The use of "acceptance criteria" only refers
Q37: Responsibility Matrices are useful for assigning and
Q38: A typical responsibility matrix will include not
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents