A Project Manager Is Building a Project Network That Involves

Question 29

Multiple Choice

A project manager is building a project network that involves testing a prototype. She must design the prototype (activity 1) , build the prototype (activity 2) , and test the prototype (activity 3) . Activity 1 is the predecessor for activity 2 and activity 2 is the predecessor for activity 3. If the prototype fails testing, she must redesign the prototype; therefore, activity 3 is a predecessor for activity 1. This is an example of


A) Conditional statements.
B) Looping.
C) Having more than one start node.
D) Good network development.
E) Natural network flow.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents