A project manager is building a project network that involves testing a prototype. She must design the prototype (activity 1) , build the prototype (activity 2) , and test the prototype (activity 3) . Activity 1 is the predecessor for activity 2 and activity 2 is the predecessor for activity 3. If the prototype fails testing, she must redesign the prototype; therefore, activity 3 is a predecessor for activity 1. This is an example of
A) Conditional statements.
B) Looping.
C) Having more than one start node.
D) Good network development.
E) Natural network flow.
Correct Answer:
Verified
Q24: Which of the following is NOT one
Q25: Arrows on an activity-on-node (AON) project network
Q26: A sequence of connected, dependent activities is
Q27: An activity that has more than one
Q28: The critical path in a project network
Q30: When translated into a project network, a
Q31: _ activities must be completed immediately before
Q32: Which of the following represents an activity
Q33: Which of the following is provided by
Q34: Even though a project network costs time
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents