When developing project networks, which of the following is not a reason for delineating technical dependencies first before doing resource dependencies?
A) The interrelationships and interactions among time and resource constraints are complex for even small project networks.
B) Resource availability may not be known until the initial schedule is completed.
C) Even if resources are known, one cannot assess the impact of limited resources until a resource-neutral schedule is created.
D) An effort to examine the interactions between technical / logical constraints and resource limitations frequently uncovers surprising problems.
E) All of these alternatives are reasons for delineating technical dependencies first before doing resource dependencies.
Correct Answer:
Verified
Q56: A project leader has realized that two
Q57: A project scheduler is trying to reallocate
Q58: All of the following are benefits of
Q59: In a resource-constrained project, the first, or
Q60: Project budgets are developed by time-phasing which
Q62: Renovation of a small compartment in a
Q63: If resource demand varies widely over the
Q64: When only one person is responsible for
Q65: Delaying noncritical activities to lower peak demand
Q66: All leveling techniques delay noncritical activities by
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents