A project scheduler is working on a project that technically allows three activities to be done at the same time. If they were to be implemented at the same time, the scheduler would need 5 contractors in order for the activities to be completed on time. There are only 3 available for the project. This is an example of what type of constraint?
A) Technical
B) People
C) Equipment
D) Physical
E) Materials
Correct Answer:
Verified
Q50: When leveling schedules to overcome resource constraints,
Q51: These are all guidelines a project manager
Q52: Which of the following is NOT one
Q53: In a resource-constrained project, which of the
Q54: In a resource-constrained project the third priority
Q56: A project leader has realized that two
Q57: A project scheduler is trying to reallocate
Q58: All of the following are benefits of
Q59: In a resource-constrained project, the first, or
Q60: Project budgets are developed by time-phasing which
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents