A bread-making factory has the production process shown in the figure below. There are five operations in sequence. The product only needs to go through one of the parallel machines in each case where parallel machines exist. What is the bottleneck time per batch of this process?
A) 50 min.
B) 60 min.
C) 35 min.
D) 30 min.
E) 20 min.
Correct Answer:
Verified
Q156: Distinguish between utilization and efficiency.
Q157: A factory produces 2000 units a month.
Q158: In the service sector, scheduling customers is
Q159: The bottleneck time is always at least
Q160: Substantial research has shown that a successful
Q162: A work system has five stations that
Q163: A tortilla chip workstation produces 1,000 chips
Q164: An assembly line has 10 stations with
Q165: In "drum, buffer, rope," the _ provides
Q166: Explain the importance of a bottleneck operation
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents