Daily usage of a part is 20 in a facility that operates 250 days of the year. Setup cost is $15 and annualized carrying cost is $100 per unit. Production of this part occurs at the rate of 50 per day when production of the part is underway. Lead time is 1 day; safety stock is 1/2 day's production. What is the optimum kanban size, and number of kanbans?
Correct Answer:
Verified
Q103: Japanese call the practice of stopping production
Q104: A bakery uses 5 kanban containers that
Q105: Which of the following is NOT an
Q106: A repetitive manufacturing firm is planning on
Q107: Employee empowerment is unnecessary in the Toyota
Q109: What are the underlying principles of Toyota's
Q110: A bakery uses 5 kanban containers that
Q111: At McDonald's and Walmart, scheduling of personnel
Q112: Which of the following is characteristic of
Q113: Because most services cannot be inventoried, there
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents