-Using Table 7.9, if the project's normal earliest completion time is to be reduced by two weeks, what is the minimum additional cost that will be incurred in achieving this two-week reduction?
A) less than or equal to $1,000
B) greater than $1,000 but less than or equal to $1,500
C) greater than $1,500 but less than or equal to $2,000
D) greater than $2,000
Correct Answer:
Verified