Solved

Table 7.9 -Using Table 7.9, What Is the Earliest Completion Time of Earliest

Question 78

Multiple Choice
Table 7.9
 
-Using Table 7.9, what is the earliest completion time of this project if normal times are used for all activities?
A) fewer than 13 weeks 
B) 13 weeks 
C) 14 weeks 
D) more than 14 weeks

Table 7.9
Table 7.9    -Using Table 7.9, what is the earliest completion time of this project if normal times are used for all activities? A)  fewer than 13 weeks B)  13 weeks C)  14 weeks D)  more than 14 weeks
-Using Table 7.9, what is the earliest completion time of this project if normal times are used for all activities?


A) fewer than 13 weeks
B) 13 weeks
C) 14 weeks
D) more than 14 weeks

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents