Instead of dividing the total standard time required to assemble each unit by nc to determine the efficiency of a line balance, you could divide by:
A) the number of workers times the number of stations.
B) the number of tasks plus the number of stations.
C) the sum of the task times plus the sum of the idle times.
D) (1-balance delay) .
Correct Answer:
Verified
Q76: Table 5.2
A company makes four products that
Q77: Table 5.2
A company makes four products that
Q78: Table 5.2
A company makes four products that
Q79: Table 5.2
A company makes four products that
Q80: Table 5.3
King Supply makes four different types
Q82: Table 5.3
King Supply makes four different types
Q83: Schmidt Industries makes four different snake traps;
Q84: The most controversial aspect of line-flow layout
Q85: Balance delay could be described as the:
A)
Q86: Instead of producing products with the highest
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents