The process batch at the constraint in a drum-buffer-rope system should be:
A) the same size as that at any non-constraint.
B) the same size as the transfer batch.
C) of such a size as to maximize the number of setups for the constraint.
D) of such a size as to improve utilization of the constraint.
Correct Answer:
Verified
Q55: The key to preserving bottleneck capacity is
Q56: Table 5.1
A company makes four products that
Q57: A bottleneck process has the lowest capacity
Q58: A firm's actual throughput and profit depend
Q59: Managers should produce products with the highest
Q61: Table 5.2
A company makes four products that
Q62: Table 5.2
A company makes four products that
Q63: Table 5.3
King Supply makes four different types
Q64: Table 5.3
King Supply makes four different types
Q65: Table 5.3
King Supply makes four different types
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents