Which of the following priority rules used in scheduling the sequence of production is calculated as the slack time remaining in the schedule divided by the number of remaining operations, with the smallest value being run first?
A) STR
B) Johnson's
C) STR/OP
D) LCFS
E) FCFS
Correct Answer:
Verified