You have just performed a CPM analysis and have found that more than one path through the project network has zero slack values. What can you conclude?
A) You have incorrectly performed the analysis.
B) You have multiple critical paths.
C) Only one path is optimal.
D) More than one path is optimal.
E) The project will not be completed by the desired time.
Correct Answer:
Verified
Q70: In this structure, team members are assigned
Q71: You know when you have arrived at
Q72: In CPM analysis, it is generally expected
Q73: You have just used the network planning
Q74: A company must perform a maintenance project
Q76: You have just used the network planning
Q77: You have just used the network planning
Q78: Which of the following is not an
Q79: You have collected the data for a
Q80: Here are the data for a time-cost
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents