Assume that an assembly line has four tasks that must be completed (in order, A, B, C, and D) . The tasks have processing times of 8, 12, 9, and 10 minutes per unit, respectively. Which task is the bottleneck?
A) A
B) B
C) C
D) D
Correct Answer: