Assume that an assembly line has three tasks that must be completed (in order, A, B, and C) . The tasks have processing times of 12, 15, and 10 minutes per unit, respectively. If the assembly line operates for 480 minutes per day with a desired output of 50 units per day, what is assembly line efficiency?
A) Less than 90%
B) 96%
C) Greater than 98%
D) Cannot be determined from the information given
Correct Answer:
Verified
Q59: Dividing assembly tasks as equally as possible
Q60: Product-focused layouts are designed to achieve?
A) High
Q61: Process-focused layouts are used for?
A) Production of
Q62: Assume that an assembly line has three
Q63: If an assembly line has an efficiency
Q65: Assume that an assembly line has three
Q66: Assume that an assembly line has three
Q67: Wait time in a process-focused layout is
Q68: A focus of material flow in a
Q69: Assume that an assembly line has three
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents