The First Step in DBR Production Scheduling Is To

Question 39

Multiple Choice

The first step in DBR production scheduling is to?


A) Identify the constrained resource(s) or bottleneck(s) in the system
B) Synchronize the release of work
C) Use inventory buffers at the critical bottlenecks
D) Forecast the demand

Correct Answer: