A project's completion time variance is calculated by?
A) Summing the variances of the critical path activities
B) Multiplying the variances of the critical path activities
C) Multiplying the variances of all of the project activities
D) Summing the variances of all of the project activities
Correct Answer:
Verified
Q32: Reducing a project's completion time by dedicating
Q33: The optimistic, most likely, and pessimistic completion
Q34: The second step to crash a project
Q35: The shortest possible time to complete an
Q36: When estimating the probability of completing a
Q38: The third step to crash a project
Q39: If an activity has a late start
Q40: A project has four activities. Activity
Q41: Project risks that are mostly within company
Q42: Lack of communication among key personnel would
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents