Complete the following table. Lead time for the part is two weeks and the order quantity is
40. What action should be taken?  Week1234 Gross Requirements20151020 Projected Available 40  Net Requirements Planned Order Receipt  Planned Order Release \begin{array}{llcc} \text { Week} &1&2&3&4\\ \text { Gross Requirements} &20&15&10&20\\ \text { Projected Available 40 } &\\ \text { Net Requirements } &\\ \text {Planned Order Receipt } &\\ \text { Planned Order Release } &\\\end{array}

Correct Answer:

verifed

Verified

An order f...