The cost-to-cost basis measures progress towards completion by


A) comparing costs incurred to date with total costs to complete the contract.
B) tracking results of work completed to date; it is an output measure.
C) tracking floors of a building completed versus floors still to be completed.
D) tracking miles of a highway completed versus miles of highway still to be completed.